Most stakeholders don’t need to understand the finer points of software testing. They’ve got their own jobs to get on with. A finance director doesn’t need to know how to prepare test data, any more than a tester needs to understand how the finance director prepares the annual accounts.
For the most part, this works well. Stakeholders get useful results, visibility of progress and enough information to make decisions. They don’t need a running commentary on everything that happens in a test environment.
However, people can expect different things from those results.
Everyone Assumes They’re Speaking About the Same Thing
Let’s take the seemingly straightforward phrase, “testing is complete.”
A business leader may hear reassurance that the release can go ahead. A developer may hear confirmation that a change works. A tester may just be reporting what they’ve checked, what they’ve found and what remains uncertain.
And then, when a stakeholder hears that all the tests have passed, do they really understand what that means? It doesn’t guarantee the trouble-free launch they’re now promising the steering committee.
The appropriate level of confidence depends on what was actually tested and under what conditions.
But there’s an even bigger misunderstanding that rears its head on way too many projects…
Stakeholders Making Changes Without Understanding Consequences
We’ve all been there: development overruns, testing is pushed, but the launch date is fixed. And so, the three weeks allocated to testing become two.
The decision is taken at a project board level. It’s only five days less, plus the test team can work later and drag in business resources to help get them over the line. The scope doesn’t change, and everyone still expects the same confidence in the release.
After all, testing is just a series of checks. Run through the scripts, see what works, report what doesn’t. Right?
Well, yes and no. Testing involves work that isn’t immediately visible in a progress report, and some of it depends on other work being completed first.
More People Won’t Make Testing Go Faster
You won’t get through Beethoven’s Ninth any faster by adding more musicians. Sure, there’s some wiggle room in the tempo, but doubling the orchestra won’t halve the performance.
Similarly, a major outsourcing company once asked us to rescue a five-day performance testing engagement for a FTSE 100 business. Two days in, testing hadn’t started. Our assessment was that the remaining time wasn’t enough. The project manager insisted it had to be done and offered hundreds of people working around the clock.
But the environment, test data and scripts still needed preparing before two days of testing could begin. That preparation depended on a few specialists who’d already been working for 48 hours straight. Nobody else had the necessary knowledge.
The project manager saw a shortage of people. The actual constraints were specialist knowledge and the time needed to complete the work.
Testing Phases Are for Developers Too
A shortened testing window can also leave room only for the happy path: everything works as expected. What if it doesn’t?
In our earlier example, the three week testing window included time for developers to fix defects and testers to check those fixes. You can’t check a fix that hasn’t been delivered. Extra testers won’t remove that dependency.
If a serious issue emerges late, the team may have to choose between delaying the release and going live with a problem that affects customers.
Factoring in Commercial Realities
Obviously, commercial priorities change, deadlines matter and, let’s be honest, some releases can get away with less testing. Phased rollouts, planned hypercare periods and increased post-go-live support can help manage the additional risk.
Test managers should be able to explain where there’s flexibility and what can reasonably be reduced. But if the business arbitrarily changes the time available, it needs to understand what else changes with it. And often, I don’t think they do. But whose fault is that?
Testers Can Help Stakeholders Understand
It’s unreasonable to expect stakeholders to understand dependencies we’ve never explained. Simply saying we need more time doesn’t give them enough information to make that decision.
If someone cuts five days, we need to explain what work will be dropped, which dependencies remain and what that means for test coverage and, ultimately, confidence in the release. The stakeholder can then consider reducing scope, moving the date or accepting the additional risk.
Dashboards can help stakeholders explore the detail behind headline results. But someone still needs to explain what those results mean for the release.
It’s their call, and testers don’t need to understand every consideration behind it. But we do need to make sure they understand what it means for testing.